Elk City Wind Farm
- SCADA Terminations in GE 1.5 MW Wind Turbine Generators
- Material procurement
- Installation of underground fiber optic splice points
- Fiber Optic Splicing of OPGW
- SCADA Terminations inside substation, MET Towers, and O&M buildings
- Complete SCADA system testing and documentation
|
|
 |
Minco Wind Farm
- SCADA Terminations in GE 1.5 MW Wind Turbine Generators
- Material procurement
- Installation of underground fiber optic splice points
- SCADA Terminations inside substation, MET Towers, and O&M buildings
- Complete SCADA system testing and documentation
|
|
 |
Dry Lake II Wind Farm
- SCADA Terminations in Suzion 2.1 MW Wind Turbine Generators
- Material procurement
- Installation of underground fiber optic splice points
- SCADA Terminations inside substation, MET Towers, and O&M buildings
- Complete SCADA system testing and documentation
|
|
 |
Keenan Wind Farm
- SCADA Terminations in Siemens 2.3 MW Wind Turbine Generators
- Material procurement
- Installation of underground fiber opitc splice points
- SCADA Terminations inside
substation, MET towers, and
O&M building
- Complete SCADA system testing
and documentation
|
|
 |
Rugby Wind
Farm 2009 Rugby, ND
- SCADA terminations in 71
Suzlon 2.1 MW Wind Turbine
Generators
- Material procurement
- Completion of underground
fiber optic splice points
- OPGW fusion splicing of
ten 72 count aerial locations
- SCADA Terminations inside
substation, MET Towers, and
O&M buildings
- Complete SCADA system testing
and documentation
|
|
 |
|
 |
|
 |
|
|
|
|
|
 |
|
 |
 |
|